Environmental Impact Assessment (Construction Environmental Permit)

Preparing and developing environmental impact assessment studies to identify potential environmental impacts during construction and operation, assess risks, and define appropriate mitigation measures.

About this service

What is an environmental impact assessment (EIA)?

An environmental impact assessment is a systematic process that predicts the environmental and social effects of a proposed project before the decision to build it. It moves through screening and scoping, a baseline description supported by field measurements, and prediction of impacts rated by their magnitude and the sensitivity of receptors.

It compares site, design and technology alternatives, proposes mitigation following the mitigation hierarchy, and ends with a management and monitoring plan that stays with the project through construction and operation.

Share

Why do you need an environmental impact assessment (EIA)?

  • The Environmental Permits Regulation requires it for the construction permit for Category 2 and 3 activities.
  • It reveals early the issues that could stop a project, such as proximity to a sensitive area or a water resource.
  • Lenders and owners rely on it for investment decisions.

What do you gain from an environmental impact assessment (EIA)?

  • Changing a design on paper is far cheaper than changing it after construction.
  • A complete study that follows the regulation's structure means fewer review rounds and comments.
  • Well-founded decisions that protect the project from objections and long-term risk.

When you need it

Before starting projects with higher potential environmental impact, to obtain the construction environmental permit and base decisions on an assessment of impacts and alternatives.

What you receive

  1. 01

    A complete environmental impact assessment study

  2. 02

    A baseline description of air, water, soil and noise

  3. 03

    Mitigation measures with a management and monitoring plan

The service includes

  • Project nature and components
  • Identifying environmental aspects and impacts
  • Air, water, soil, and noise assessment
  • Identifying potential risks
  • Mitigation and treatment measures
  • Preparing required reports and studies

Regulatory requirements

NCEC requirements

Reference authority

National Center for Environmental Compliance (NCEC)

An environmental impact assessment is required for Category 2 and 3 activities to obtain the construction permit; NCEC sets the category after reviewing the classification form.

  • Category 2: an impact assessment following Appendix 2; NCEC decides within 30 working days.

    Environmental Permits Regulation — Art. 7 · p. 11

  • Category 3: a scoping report first (15 working-day review), then the full study under Appendix 4, decided within 60 working days.

    Environmental Permits Regulation — Art. 8 · pp. 12–13

  • The study and all related analyses, tests and measurements must be carried out by an NCEC-licensed service provider.

    Environmental Permits Regulation — Art. 3(13) · p. 7

  • Sampling and measurements follow the methods in the executive regulations, or USEPA methods where none are set.

    Permits issuance and renewal guide — p. 8

  • The construction permit is valid for 3 years, extendable by 2 for large projects when requested in the study.

    Environmental Permits Regulation — Art. 6 (Second/8) · p. 10

  • The applicant must implement the study's findings; impact assessment starts at feasibility and concept design, without splitting the activity into parts.

    Environmental Permits Regulation — Arts. 7 and 9 · pp. 12–13

A summary for guidance with page numbers in the official documents; the binding text is the document issued by the authority, which may be updated.

Official documents to download

Environmental guideline for preparing environmental impact assessment studies

National Center for Environmental Compliance (NCEC)

Document code EP-M-43-V01

PDF42 pages1.5 MBArabic

Guide to issuing and renewing environmental permits to establish and operate activities

National Center for Environmental Compliance (NCEC)

Issued under Article 3 of the Environmental Permits Regulation

PDF26 pages1.3 MBArabic

Executive Regulations for Environmental Permits to Establish and Operate Activities

National Center for Environmental Compliance (NCEC)

Environmental Law — the violations and penalties table (Table 2) was later amended by ministerial decision

PDF27 pages1 MBEnglish

How we deliver it

How we deliver

  1. 1

    Activity review and screening

    We review the project's nature, location and stage to define the studies and permits required and the scope of each.

  2. 2

    Baseline data and site visits

    We build the environmental baseline from site visits, measurements and reliable secondary sources.

  3. 3

    Assessment and analysis

    We identify environmental aspects and impacts, rate their significance, and define mitigation and monitoring.

  4. 4

    Report preparation and submission

    We prepare the study or plan to the applicable requirements and support submission and responses to review comments.

  5. 5

    Follow-up and compliance

    We help implement permit conditions, keep records current and run periodic audits across the project's life.

Request a consultation

Request a consultation or quote for this service

Share your project details and the Delta Built team will reach out to understand your needs and agree the next step.

  1. 1. Your need
  2. 2. Your project
  3. 3. Contact

Which service do you need?

Choose the service, then the scope. If you are not sure, choose “Help me choose” and a consultant will suggest the right service.

Environmental Consulting & Compliance
Choose the scope (more than one is fine)

Scope directly covered by NCEC requirements